4
Addendum
e)
The date of assembly.
f)
The maximum number of simultaneous working platforms permitted.
g)
The maximum number of persons permitted on the working platform(s)
during use.
h)
The maximum number of persons permitted on the tower during assembly
and dismantling.
i)
The maximum number of persons permitted on any one platform.
j)
The maximum safe working load on the working platform.
k)
The maximum safe working load on the prefabricated tower scaffold.
l)
The load class of the prefabricated tower scaffold.
m)
The maximum horizontal force permitted at the working platform(s).
n)
The maximum wind limits for working on the prefabricated tower scaffold.
o)
The maximum wind limits for the prefabricated tower scaffold.
Mandatory information, required to gain certification to BS 1139-6:2022.
When moving the tower:
•
Maximum windspeed = 0mph
•
Maximum slope = 0°
•
Maximum platform height = 2.2m
Explanatory Note
This tower may be moved when a wind is blowing, when there is a slope
and with platform heights greater than 2.2m, but many factors contribute to
safe movement. It is not possible to give maximum figures that apply in all
circumstances. See section 3.4 above. A task risk assessment should be
made.
When working on the tower:
•
Maximum windspeed = 0mph
Explanatory Note
It is possible to work on the tower at windspeeds greater than 0mph. The safe
working windspeed will depend on the work being undertaken. A task risk
assessment should be made.