Installation Guide; Installation Precautions; Installation Requirements - Huawei NetCol8000-E220 User Manual

Modular indirect evaporative cooling system
Hide thumbs Also See for NetCol8000-E220:
Table of Contents

Advertisement

NetCol8000-E220 Modular Indirect Evaporative
Cooling System
User Manual

4.1 Installation Precautions

4.1.1 Installation Requirements

Installation Precautions
Checking the Auxiliary Facilities
Checking the Drainage Capacity
There should be drainage ditches with sufficient drainage capacity.
Issue 10 (2024-01-30)
Before installing the unit, place it in a dry, rainproof, fireproof, and
anticorrosive environment.
Protect the product during delivery. Do not step on or damage vulnerable
parts such as fan guards or air filters.
Ensure that the bottom of the unit is completely placed on the ground or the
unit is supported at six points when it is being installed.
Do not damage the materials used for protecting the unit during
transportation before hoisting it.
If the unit will be stored for more than three months, place it in an area with
a ceiling or protect it with a tarpaulin.
When installing the unit outdoors, avoid damaging the protective film on the
surface.
Do not stack whole units together.
Check the unit periodically.
It is recommended that the strength level of the concrete foundation be
higher than C20.
The surface of the concrete foundation should be flat and clean.
Copyright © Huawei Digital Power Technologies Co., Ltd.
4

Installation Guide

4 Installation Guide
34

Advertisement

Table of Contents
loading

Table of Contents