TEST RUN

TEST RUN
Checkpoint before test run
Start the chiller after checking the following.
- Before starting the chiller, check the supplementary devices such as cold water circulation pump,
AHU or other devices. Refer to the directions from the manufacturer. If all equipped parts are
installed on the device, check whether all parts are installed appropriately and accurately and
check whether the wiring is done correctly. Refer to the wiring diagram of the product.
- Check the flow switch for appropriate operation of the product. Check whether the sensor is
operating properly.
- For cooling, fill up cold water circuit with clean water or other non-corrosive liquid and purge the
air so that there is no air remaining inside the cold water circuit. If the outdoor temperature is
expected to drop below 0 °C (32 °F), add anti-freeze additive to the cold water circuit to prevent
the water from freezing. Cold water circuit must be cleaned before connecting to the product.
- Check and inspect all water pipes. Check whether the direction of the water flowing is correct
and whether properly connected to the evaporator. Open all flow valves to the evaporator side.
- When the outdoor temperature in winter falls below 5 °C (41 °F), take measures to prevent
freezing of water pipes.
- Freeze protection measures such as antifreeze injection, heater operation, and pump operation
are required.
- Turn on the cold water pump and measure the overall water pressure reduction of evaporator to
check whether the flow is accurate compared to the designed flow rate.
- Check all electric connections within the control panel and whether all parts are tightly
assembled with good contact conditions. Though the connecting part is checked from the
factory but it can be loosened during the transportation from the vibration.
- Check and inspect all fuses. All fuses within the power panel and control panel must be
installed at appropriate location.
Starting procedure
The chiller can be started as follows.
- Check whether the load is operating on the air processing device or other device on the side of
the water that supplies the water to the chiller. If the temperature of the cold water is too high,
the start of the load device on the water side can be delayed.
- If auto control does not work from the chiller, check whether the water circulation pump is
operating.
- Voltage variance must be within 10 % and check that the phase voltage imbalance does not
exceed 5 % between phases. Check whether the power and capacity is appropriate for
processing the load.
- Check the order of the power phase.
- Check and inspect the voltage monitoring meter within the power panel. The meter should not
show any error code.
- Use the HMI device to check the cold water outlet temperature and cooling water output
temperature setting.
- Set the start menu of HMI device to start the system. Water circulation flow must be within the
permitted range to control the temperature appropriately.
128
Due to our policy of continuous product innovation, some specifications may change without notification.
©LG Electronics U.S.A., Inc., Englewood Cliffs, NJ. All rights reserved. "LG" is a registered trademark of LG Corp.

Advertisement

Table of Contents
loading

Table of Contents