Tube Installation Sequence
Chart 2.2
•
Tube Installation Sequence, Baffle Location, and Secured Joints for Reflectors
20 Foot
25 Foot
30 Foot
40 Foot
50 Foot
60 Foot
70 Foot
Burner Control Box
w/16 in. Burner Tube
Expansion Joint on
Reflectors
Secured Joint on
Reflectors (see note)
Primary Combustion
Chamber with Clamp
*
Stainless steel clamp on 150,000 BTU/h models (P/N:
TP-220).
*
Stainless steel clamp on 150,000 to 200,000 BTU/h
models (P/N: TP-220).
*
Stainless steel clamp on 150,000 to 200,000 BTU/h
models (P/N: TP-220).
*
Stainless steel clamp on 200,000 BTU/h models (P/N:
TP-220).
2.0
Installation
NOTE: When securing joints on reflectors which are
rotated on an angle from horizontal, secure joint
only on top side of reflector to allow for sufficient
heater expansion and contraction.
0° Mounting Angle
Key
Radiant Tube
Exchanger with Clamp
Baffle Location
Secure vent material to exchanger with three #8
sheet metal screws. Seal with high temperature
silicone sealant. Do not use tube clamp.
*
A secondary combustion chamber is installed as the
second tube downstream from the burner control box on
150,000 to 200,000 BTU/h models.
11
•
Tube Installation Sequence
1° to 45° Mounting Angle