Good lifting practices and lifting aids should be used as required to aid installation. Important Notes The symbols below show important notes that must be read and understood at each stage of installation = Warnings (Safety or Installation Quality) = Information (Installation requirements or tips) Dynamic 4 Installation Manual – DRAFT...
Page 3
Note that the Dynamic 4 is designed and recommended to be assembled on the wall so that a clear floor area big enough to build the screen is not required. However, it can also be built on the floor if preferred you will just need to follow the same instructions but substitute the wall for the floor then lift and attach the screen to the wall once built.
• Using a spirit level, ensure that the left side section is vertical. • Screw the left section to the wall using the fixing holes in the back plate. Dynamic 4 Installation Manual – DRAFT...
Page 6
The top screen section must he help up by the installer until fixed in place and not held up by the stretcher bar. This is a guide only. Dynamic 4 Installation Manual – DRAFT...
Page 7
You should now have 3 sections fixed looking like this: Note that this image is of a Dynamic 2. On a Dynamic 4 you will not have the velvet top and bottom cover fitted at this point. Fix the Right section to the top and bottom sections again with the sliders ensuring that you •...
Page 8
Ensure that the masks are both now under tension and that no wiring has become loose in transit or during installation that will impede the travel of the mask bar along the linear bearing track it travels on. Dynamic 4 Installation Manual – DRAFT...
M12 Screw sensor cable. Simply connect this and screw together the connector to lock. Ensure that the electrical connections for the Side masks and the tension springs are all in place before you fit the top and bottom masks Dynamic 4 Installation Manual – DRAFT...
Page 10
Now in the same way you fitted the bottom mask, fit the top mask ensuring that you tighten all the M8 fixing bolts. Due to gravity pulling down on the top profile larger screens will need 2-3 people top hold the top mask profile up while the locking bolts are attached. Dynamic 4 Installation Manual – DRAFT...
Page 11
Care should be taken to ensure that the connections are connected correctly according to the colour coding on the plugs. • Ensure that all the electrical connectors on the screen are connected at this stage. Dynamic 4 Installation Manual – DRAFT...
Page 12
Any misalignment can be sassily resolved by sliding the covers on the magnet fixings to ensure perfect joints. Now fit to top left and right ‘L’ sections in the same way to complete the frame. • Dynamic 4 Installation Manual – DRAFT...
This will free it and continue with the initialisation sequence. The screen is now ready for operation and external RS232 control of operation. • Dynamic 4 Installation Manual – DRAFT...
Page 15
Only tuck max 300mm at a time in each direction and then go to the opposing side and tuck the same amount. This will ensure an even stretch across all the fabric. Dynamic 4 Installation Manual – DRAFT...
Page 16
Ensure that you use the white cotton gloves to handle the white projection fabric at all times and keep it away from dust or dirt as it can easily be marked. Dynamic 4 Installation Manual – DRAFT...
Need help?
Do you have a question about the Dynamic 4 and is the answer not in the manual?
Questions and answers