Installation
Foundation
The following information are guidelines only
and are not intended to be used as foundation
specifications.
•
The floor should be level within ±0.5 in. and
made of reinforced concrete (not asphalt) no less
than 4 inches thick. If the existing floor is not of
sufficient thickness or is not level, a new floor
should be poured.
•
The soil under the concrete floor must be well
settled so the load of the machine and the floor
do not cause further settling. This is especially
important when pouring a new floor.
•
Newly poured concrete floors need ample time
to cure before installing the machine.
•
Routing of in-floor conduits or utility trenches
must be done in a manner not to weaken the
flooring the area or the machine.