10. Installation
Outdoor unit installation
WARNING
• Make sure to remove the wooden pallet before installing the outdoor unit. If you do not remove the wooden
pallet, there is risk of fire during welding the pipes. If the outdoor unit is installed with wooden pallet on, and it
was used for long period time, wooden palette may break and cause electrical hazard or high pressure may
damage the pipes.
※ Fix an outdoor unit firmly on the base ground with anchor bolts.
※ Manufacturer is not responsible for the damage occurred by not following the installation standards.
1 Make sure that the height of the base ground is 200mm (8inch) or higher to protect the outdoor unit from rain water
or othe external conditions. Also, install a draining pit around the base ground and connect the drain pipe to the drainage.
2 Considering the vibration and weight of the outdoor unit, strength of the base ground must be strong to prevent noise and
the top surface of it should be flat.
3 Base ground should be 1.5 times larger than the bottom of the outdoor unit.
4 Outdoor unit must be fixed firmly so that it can withstand the wind speed of 30m/s. If you cannot fix the outdoor unit on the
base ground, fix it by side or use extra structure.
5 In heating operation, defrost water may form so you must really care about the drainage and waterproofing the floor.
To prevent defrost water from stagnating or freezing, construct a drainage with over 1/50 slope. (Ice may form on the floor in
winter season.)
6 It is necessary to add wire mesh or steel bar during concrete construction for the base ground to prevent damages or cracks.
7 When installing multiple outdoor units at the same place, construct an H beam or an anti-vibration frame on the base ground
to install the outdoor unit.
8 After installing an H beam or an anti-vibration frame, apply corrosion protection and other necessary coating.
9 When concrete construction for outdoor unit installation is completed, install an anti-vibration pad (t=20mm/0.78inch or
more) or an anti-vibration frame to prevent vibration of the outdoor unit from transferring to the base ground.
10 Place the outdoor unit on an H beam or an anti-vibration frame and fix it with the bolt, nut and washer. (The bearing force
has to be over 3.5kN)
Base ground construction
Draining pit
Over 200 (8)
<When installing on the ground>
Unit : mm (inch)
Bottom surface of the base ground
must be horizontally leveled
Over 200 (8)
<When installing on the roof>

Advertisement