Installing The Zoneline - GE Zoneline AZ9VH Owner's Manual And Installation Instructions

Vertical air conditioner
Hide thumbs Also See for Zoneline AZ9VH:
Table of Contents

Advertisement

Available languages

Available languages

Installing the Zoneline

1.
locations.
2.
3.
4. Complete condensate drain connections.
5.
6. Connect the top ductwork.
1. Plan for proper electrical supply, drains and ductwork locations.
1. Complete rough in plumbing for primary and secondary condensation drains.
2. Install the Louver and Wall Plenum
1.
Refer to instructions included in the louver kit RAVAL4 or RAVAL3 for proper installation procedures.
2.
Refer to instructions included in the wall plenum kit RAVWPT15B for proper installation procedures.
3. Install and Level the Drain Platform
1.
Condensate Disposal System
condensate onto the hot outdoor coil.
When high outdoor humidity prevents the slinger from disposing of all condensate, the excess condensate overflows
NOTE: If the primary drain system fails to remove all of the condensate from the unit, any excess condensate
will overflow from the drain pan into the secondary drain (if connected), and drain outside the building. This
is your indication that the chassis or drain requires servicing.
INSTALLATION SUMMARY
INSTALLATION INSTRUCTIONS
7. Connect the remote thermostat.
8. Connect auxiliary features, if required.
9. Make electrical connections to unit.
10.
11. Review the final installation checklist.
12.
13.
49-5000640 Rev. 2

Advertisement

Table of Contents
loading

Table of Contents