Trane RTXC-XE Series Installation, Operation And Maintenance Manual page 3

Air-cooled screw chiller heat pump
Table of Contents

Advertisement

Installation Completion and Request for Trane Service
Important: A copy of this completed form must be submitted to the Trane Service Agency that will be responsible for the
start-up of the equipment. Start-up will NOT proceed unless applicable items listed in this form have been satisfactorily
completed.
TO: _________________________________________________________
Trane SERVICE OFFICE:_____________________________________
S.O. NUMBER: _____________________________________________
SERIAL NUMBERS:_________________________________________
JOB/PROJECT NAME:_______________________________________
ADDRESS:__________________________________________________
The following items are being installed and will be completed by:
Important: Start-up must be performed by Trane, or an agent of Trane specifically authorized to perform start-up and
warranty of Trane® products. Contractor shall provide Trane (or an agent of Trane specifically authorized to perform start-
up) with notice of the scheduled start-up at least two weeks prior to the scheduled start-up. Equipment not started by
Trane is not warranted by Trane.
Check box if the task is complete or if the answer is "yes" .
Unit location
□ Provide enough space around unit to allow unobstructed air flow
□ Unit mounting placed on a rigid and level foundation
□ Isolator installed and fully tightened
□ Secure no external vibration transmitted to the unit
□ Provide enough space around unit for installation and service personnel unrestricted access
Wiring
□ Wiring size per all national or local codes and equipped with the remote fused disconnect switches
□ Inspect all wiring connections to ensure correct and tight
□ Ground all customer supplied power wires as required by applicable codes
□ Distance between low voltage line and power wiring meet required
□ Check wiring connections corrected and tightened before power on
□ Provide separately power for anti-freeze heater of evaporator, PHR BPHE or water pipes
Piping
□ Water system designed by professional designers, such as piping diameter etc.
□ Water pump head match actual water side resistance
□ Water strainer installed before inlet of the unit and cleaned prior to connection
□ Water pressure gauges installed with shutoff valves to monitor evaporator pressure drop
□ Vibration eliminators equipped to prevent vibration transmission through the water pipes
□ Air vent, drain and feed valve at the right position of water system
□ Meet minimum water loop volume of 9 liter/kW to stable leaving water temperature for comfort cooling
□ Thoroughly flush all external water piping before final piping connecting to the unit
□ Pass water system pressurization test and no water leakage identified
□ Water system filled and air bled from system
□ Anti-freeze protection active after water system filled in winter
□ Flow switch installed (if not factory-provided)
□ External interlocks (flow switch, pumps auxiliary, etc.) per Wiring Schematics of the manual
□ Water piping insulated and fixed
□ Evaporator bypass valve installed as required (if installed)
RTXC-SVX003D-EN
3