Start-Up; Contents Of This Chapter; Start-Up Procedure - ABB ACS880-107 Hardware Manual

Inverter units
Hide thumbs Also See for ACS880-107:
Table of Contents

Advertisement

Start-up 99

6
Start-up

Contents of this chapter

12
This chapter describes the hardware commissioning of the inverter unit. For
information on setting up the control program, refer to the appropriate firmware
manual. For information on commissioning the supply unit, refer to its hardware
manual.

Start-up procedure

The tasks which are needed in certain cases only are marked with underlining, and
option codes are given in brackets. Default device designations (if any) are given in
brackets after the name, for example "main switch-disconnector (Q1)". The same
device designations are also used in the circuit diagrams.
These instructions cannot and do not cover all possible start-up tasks of a customized
drive. Always refer to the delivery-specific circuit diagrams when proceeding with the
start-up.
Note: For some options (such as safety options +L513, +L514, +L536, +L537, +Q950,
+Q951, +Q952, +Q957, +Q963, +Q964, +Q965, +Q966, +Q978, +Q979), additional start-up
instructions are given in their separate manuals.