Figure 6-65 Positions of the eLight actuator and power supply
(1) AC actuator
Procedure
Step 1 Label each cable based on the corresponding ports on the eLight actuator.
Step 2 Remove cables from the eLight actuator.
Step 3 Remove the old eLight actuator from guide rails.
Step 4 Install the spare eLight actuator in the original position and connect the cables.
Step 5 Check the parameters and communication status of the eLight actuator to ensure normal
communication.
Step 6 On the ECC800 WebUI, choose Maintenance > Opening Guide > Linkage Test > eLight
actuators Commissioning and click Test. The eLight strip light is lit up in red, green, blue,
and white in sequence for 3 seconds respectively, and then turns off.
----End

6.4.21 Replacing an eLight Power Supply

Impact on the System
The eLight strip light is off during replacement.
Issue 05 (2020-03-25)
(2) eLight actuator
Copyright © Huawei Technologies Co., Ltd.
6 Parts Replacement
(3) eLight power supply
108

Advertisement

Table of Contents
loading

This manual is also suitable for:

Fusionmodule2000

Table of Contents