Step 8 Verify that the rPDU power output is normal and then connect the IT load cables to the rPDU.
----End

6.2.5 Replacing a Smart rPDU

Impact on the System
One power input of the equipment cannot work.
Preparations
Context
The smart rPDU is installed near the rear door of the cabinet.
Procedure
Step 1 Open the rear door of the cabinet.
Step 2 Connect the IT load of the faulty smart rPDU to a normal rPDU.
Step 3 Turn off the industrial connector for the faulty smart rPDU. Ensure that the smart rPDU input
has no power.
Step 4 Remove signal cables from the ports on the smart rPDU and label the cables.
Step 5 Remove the screws that secure the smart rPDU using a Phillips screwdriver.
Step 6 Secure the new smart rPDU in the installation position of the old smart rPDU.
Step 7 Connect the input power cables and signal cables to the new smart rPDU.
Step 8 Turn on the upstream power distribution switch for the smart rPDU and the smart rPDU input
switch.
Step 9 Verify that the smart rPDU power output is normal and then connect the IT load cables to the
smart rPDU.
----End

6.2.6 Parts Replacement for the New Main Way

There could be service interruptions during the replacement of the new main way. If power
disconnection is required, seek the customer's permission first.
Issue 05 (2020-03-25)
Tools: Phillips screwdriver, step ladder, label, marker
Material: smart rPDU of the same specifications