3.4. Checking hoist operation before commissioning
Before hoist commissioning, hoist service responsible has to check if hoist is in compliance with
following points:
Hoist is installed with all operational safety systems:
Portable control buttons work correctly
Superior endtrack switch stops hoist before reaching superior endtrack buffers.
Inferior endtrack switch stops hoist before reaching base buffers.
Mast presence detector works correctly.
OUT OF SERVICE red light indicator works correctly.
No existen interferencias entre el elevador y elementos exteriores, mástil, anclajes,
There´s no interference of hoist and external items, mast, ties, supporting structure.
Inferior access area to the hoist is demarcated and protected properly.