Install Cabinets

This section is a guide to mounting the cabinets onto the Mounting bar and describes the following
in more detail:
Prepare the cabinets for installation.
Install the first row of cabinets
Fix the first row of cabinets to the Power bar.
Install further cabinets.
Align all cabinets of the LED Wall to achieve an even surface.

Table 9: Cabinet Installation Requirements

No. of People 2
Prerequisites
Frameset securely installed
Power bar securely installed
Tools
Screwdriver
Allen key
Equipment
Cabinets
Cabinet hanger pins
Adjustment plate
13 
9 
5 
1 
Figure 47: Wall Mounting: Installation Order of Cabinets (4×4 Frameset)
6.3.1

Install Cabinet Hanger Pins on the Backside

On the workbench, place cabinet front-side
down on a protected surface.
Step 1)
Install Cabinet hanger pins (2×) on
top left- and right-hand corners.
Step 2)
Secure the Cabinet hanger pins
firmly.
14 
15 
10 
11 
6 
7 
2 
3 

Figure 48: Installing the Cabinet Hanger Pins

16
12
8