1MRK 505 339-UEN B
actual signal voltage present on the input. For outputs, any output relay can be forced to be
active or not, regardless of the current requested state of the output in the IED logic
configuration.
9.8.2

How to enable forcing

To enable forcing, the IED must first be put into IED test mode. While the IED is not in test
mode, the LHMI/PCM600 menus that relate to forcing will not have any effect on the input/
output status due to safety reasons.
9.8.2.1

Enable forcing by using LHMI

1.
Enable IED Testmode by setting
mode TESTMODE:1.
IEC15000029 V1 EN-US
2.
Exit back to the root menu.
3.
Select
Once the IED is in test mode the yellow Start LED starts to blink.
9.8.2.2

Enable forcing using TESTMODE function block

Use the TESTMODE function block, appropriately configured in PCM600/ACT.
It may be convenient to control the input on mentioned component from, for example, an LHMI
function key or similar during commissioning to quickly and easily enter IED test mode.
9.8.3

How to change binary input/output signals using forcing

Once the IED is in IED test mode, the LHMI/PCM600 menus can be used to control input/
output signals freely.
Commissioning manual
Be observant that forcing of binary inputs and outputs on an IED, with
inappropriate setup, can result in potential danger.
Yes in the save dialogue box.
IEDTestMode to On under Main menu/Test/IED test
Section 9
Testing IED operation
GUID-50280F59-A98C-4E48-AB6D-2B4C138943DD v1
GUID-41F7C636-75BC-42EF-A955-4BD9E347619E v1
GUID-DD17B7D6-516F-4561-9D30-906B968EAFE0 v1
GUID-7DF9FAF1-68B1-49AF-9DE4-2A8D6F6FAEFE v1
63