e) Is water pressure appropriate?
In case inlet water pressure is higher than 0.6 MPa, install a pressure regulator.

3.2.- START-UP

Once the installation instructions are followed (ventilation, site conditions, temperatures, water quality,
etc.), proceed as follows:
1.- Open the water inlet. Verify the no existence of leakages.
2.- Open the door and remove the protection elements on the curtain.
3.- Verify that the curtain moves freely.
4.- Connect the machine to the power supply.
5.- Push the switch on the machine front side.
6.- Verify that there are no vibrations or frictions on the elements.
7.-
Close door
8.- Verify the ice cubs with the pictures below. Adjust production time switches (see table in 4.1, switches
1-4 (tf)) to make the ice cubes with the right shape.
Too big
Damages due to the lack of maintenance and cleaning operations are not included on the warranty.
MINIMUM
10ºC
MINIMUM
MAXIMUM
Just right
10ºC
0.1MPa (1 bar)
0.6
MPa
(6
bar)
Too small
12