Tests

Verify programming
Verify that the zones are correctly programmed at the control panel.
Sample test a few mapping configurations.
System test
Test the system by following the quarterly maintenance test routine described in
the ZP3-ECU Maintenance Manual.
Arm the system
Once you are sure that the system is functionally correct, connect the actuator,
and make sure that the transit pin (if fitted) is removed.