Chapter 3: Commissioning

Introduction

The commissioning of the ECU is done by performing a number of logical steps.
These must be done in the sequence provided to successfully complete the task.
Caution:
Once the ECU is connected, the wiring must NOT be meggered. This
will cause irreparable damage to the circuit.

Prerequisites

Before commissioning, make sure of the following:
The small hand tools are available for testing, connecting, disconnection, etc.
That a good multimeter (preferably digital) is at hand.
That you have all information relating to system zoning, relay mapping, relay
operating parameters, device sensitivity settings, etc. properly documented.
That the drawings on hand indicate correct device positions, device
addresses, and device types with all relevant wiring runs.
That the actuator is NOT connected to the ECU. For commissioning purposes
use a 2K2 Ω EOL (end-of-line) resistor in series with a LED (or the multimeter
across the resistor) to monitor the voltage at the location of the actuator.
DO NOT connect power to the ECU.
DO NOT connect power to the fire alarm control panel to which the ECU is
connected.
18
ZP3-ECU Extinguishing Control Unit Installation and Commissioning Manual