Routing Cables/Hoses For Water-Cooled System - Lenovo ThinkSystem Heavy Duty Full Depth 48U User Manual

Rack cabinet
Table of Contents

Advertisement

Cable access openings on extension panel
Figure 99. Cable access openings on extension panel
There are five 89 (width) x 178 (height) mm openings on each side panel:
• U7 to U11
• U13 to U17
• U25 to U29
• U32 to U36
• U42 to U45

Routing cables/hoses for water-cooled system

Adopt one of the following procedures, depending on whether the rack is in a raised-floor environment.
Important: To help maintain optimal performance and provide proper cooling for all rack components,
always take the following precautions:
• Install filler panels over all unoccupied bays.
• Route signal cables at the rear of the rack so that they enter or exit the cabinet through the top and
bottom air baffles.
.
89
Chapter 4
Managing cables and hoses