Adding disk 2.13 to the cache tier...done
Updating system information...done
Disk 2.13 successfully added to the cache tier.
Checking storage requirements...done
Adding disk 2.14 to the cache tier...done
Updating system information...done
Disk 2.14 successfully added to the cache tier.
Checking storage requirements...done
Adding disk 2.15 to the cache tier...done
Updating system information...done
Disk 2.15 successfully added to the cache tier.
Install and connect the new storage
Verify a license exists for the new capacity before attempting to add it to the system.
Complete the following tasks to add new storage capacity to the system.
Install the new disk shelves in the rack
NOTE:
This task does not apply when adding a new disk pack to an existing DS60 shelf.
Complete the steps in
Install the Disk Shelves in the Rack
Cabling diagrams
Connect Cables and Power On
Power cycle DS60 shelves
About this task
To make sure that the shelf firmware is updated properly, power cycle DS60 shelves after installing them. Complete the
following tasks to power cycle the shelves.
NOTE:
The KB article Data Domain Restorers with DS60 shelves may encounter a kernel panic due to an LCC firmware
change, available on https://support.emc.com, provides additional information.
Steps
1. Run the system poweroff command to shutdown the Data Domain system.
2. Remove all AC power cords from all DS60 shelves for 30 seconds.
3. Reconnect the AC power cords to the DS60 shelves and wait five minutes for the shelves to power up and stabilize.
4. Power on the Data Domain system
5. Log back in as a sysadmin user.
on page 53 provides cabling diagrams, and instructions.
on page 25 to install a new disk shelf in the rack.
Add Storage Capacity
91