Leak Test; Fail-Safe Position; Pressure Test - Samson 3354 Mounting And Operating Instructions

Globe valve
Table of Contents

Advertisement

To test the valve functioning before start-up
or putting back the valve into operation, per-
form the following tests:
5.4.1

Leak test

The plant operator is responsible for per-
forming the leak test and selecting the test
method. The leak test must comply with the
requirements of the national and internation-
al standards that apply at the site of installa-
tion.
Tip
Our after-sales service can support you to
plan and perform a leak test for your plant.
1. Close the valve.
2. Slowly apply the test medium to the inlet
space upstream of the valve. A sudden
surge in pressure and resulting high flow
velocities can damage the valve.
3. Open the valve.
4. Apply the required test pressure.
5. Check the valve for leakage to the atmo-
sphere.
6. Depressurize the pipeline section and
valve.
7. Rework any parts that leak and repeat
the leak test.
EB 8140 EN
5.4.2

Fail-safe position

Î Shut off the signal pressure line.
Î Check whether the valve moves to the
fail-safe position (see the 'Design and
principle of operation' section).
5.4.3

Pressure test

The plant operator is responsible for per-
forming the pressure test.
Tip
Our after-sales service can support you to
plan and perform a pressure test for your
plant.
During the pressure test, make sure the fol-
lowing conditions are met:
− Retract the plug stem to open the valve.
− Observe the maximum permissible pres-
sure for both the valve and plant.
Installation