11. INSTALLATION
11.1 ELECTRICAL CONNECTIONS
Product installation must be carried out by
a qualified technical professional.
YES
The controller MUST be installed:
- In an indoor and dry environment;
- Away from electromagnetic fields;
- In a ventilated place, free from flammable
liquids and gases;
- Protected by a circuit breaker of the
appropriate specification for the installed
load.
Failure to comply with the warnings will cause loss of warranty,
material and/or physical damage.
T1 - SENSOR T1
D4 - DIGITAL INPUT
1
2
3 4
5 6
T1
IMPORTANT: Check power according to the product model.
ATENTTION! Before removing the protective cover,
disconnect the mains from the controller.
Note: The sensor cable length can be extended by the user up to 200 meters using PP 2 x
24 AWG cable.
11.2 IMPORTANT
According to chapters of the NBR 5410 standard:
1: Install surge protectors in the supply.
2: Sensor and serial communication cables can be together, but not in the same conduit
through which electrical power and load activation pass.
3: Install transient suppressors (RC filter) in parallel with the loads, in order to increase the
life of the relays.
Connection diagram of suppressors
in contactors
A1
A2
A1 and A2 are the contactor
coil terminals.
Full Gauge Controls offers suppressors for sale
11.3 OVERLAY INSTALLATION
Remove the protective cover from the connections
1
on the bottom of the controller.
Detach the openings at the bottom necessary for
2
the cables to pass through.
Fix the controller to the wall using screws and
3
wall plugs.
NO
Controller MUST NOT be
installed:
- In a humid environment;
- Exposed to the sun or rain;
- In saunas, engine rooms or
bathrooms.
10 11
12 13
AUX
230 Vac
0
or
D4
115 Vac
Connection diagram of suppressors in
direct drive loads
Loads
For direct activation, take into account
the specified maximum current.
To find the position of the first hole, mark 4 points on
the wall using the indications on the product as a
reference.
Make the electrical connections
4
of the controller.
5
For a better finish, install wire channels (20x10mm).
Position the electrical connection protection cover
6
and secure it with the screw (included in
the package).
11.4 4X2 BOX INSTALLATION
Remove the protective cover from the
1
connections on the bottom of the controller.
Make openings for cables to pass through in
2
the indicated regions on the back of the controller.
Route the cables through the openings as per the controller
connections.
Fix the controller in the 4x2 box with screws.
3
The top screw must not be fully screwed in, in order to allow
the controller to fit in. After attaching the controller to the
upper screw, secure it with the lower screw.
Make the electrical connections
4
of the controller
The power supply and load
activation connections are
protected by mechanical
barriers.
For the use of eyelet-
type terminals, the
barriers can be
removed using cutting
pliers.
The power supply and
load activation
connections are protected
by mechanical barriers.
For the use of eyelet-
type terminals, the
barriers can be
removed using cutting
pliers.
Need help?