Ensure that the power voltage of the smart array controller is within the operating voltage range,
and the three-phase input voltage is within the MBUS/PID module operating voltage range.
1. Turn on the single-phase power switch that controls the power supply from the remote
transformer station to the smart array controller.
2. Turn on the three-phase power switch that controls the power supply from the remote
transformer station to the smart array controller.
If the smart array controller houses one PID module, turn on the corresponding three-phase
power switch.
If the smart array controller houses two PID modules, turn on the corresponding three-phase
power switches.
3. Check that the input voltages of all switches of the smart array controller are within appropriate
operating voltage ranges using a multimeter.
4. Turn on the QF03 single-phase input switch in the smart array controller.
6. Turn on the PID switch in the smart array controller.
If the smart array controller houses one PID module, turn on the QF01 PID switch.
If the smart array controller houses two PID modules, turn on the QF01 and QF02 PID
switches.
7. Turn on the three-phase input switch in the smart array controller.
If the smart array controller houses one PID module, turn on the FU01 three-phase input
switch.
If the smart array controller houses two PID modules, turn on the FU01 and FU02 three-phase
input switches.
Commission the PID module after powering it on. For the detailed commissioning
procedure, see chapter 9 "Commissioning the SmartPID2000."
For details about the status of the energized SmartLogger and MBUS CCO
module as well as the commissioning procedure, see the
Manual
. When the smart array controller communicates with the solar inverter
over MBUS, log in to the embedded WebUI of the SmartLogger3000, choose
Monitoring > MBUS > Networking Settings, and set Networking to Enable
(default value). When the smart array controller communicates with the solar
inverter only over RS485, set Networking to Disable.
The Ethernet switch can be directly put into use without commissioning after
power-on.
9
Commissioning the SmartPID2000
The SmartPID2000 can be commissioned over the embedded WebUI of the
SmartLogger, by connecting the SUN2000 app to the SmartLogger, or by connecting
the SUN2000 app to the PID module. This section describes how to commission the
SmartPID2000 by connecting the SUN2000 app to the SmartLogger.
The app has been connected to the SmartLogger over WLAN. Log in as installer
and access the Home screen of the SmartLogger. For detailed operations, see the
SmartLogger3000 Quick Guide
appropriate
The following uses SUN2000 app 3.2.00.003 (Android) and SmartPID2000
V100R001C00SPC102 as examples.
Use the initial password upon first power-on and change it immediately after
login. To ensure account security, change the password periodically and keep the
new password in mind. Not changing the initial password may cause password
disclosure. A password left unchanged for a long period of time may be stolen or
cracked. If a password is lost, devices cannot be accessed. In these cases, the user
is liable for any loss caused to the PV plant.