Advertisement

Electricity prices and gas price
About energy prices in case of an incentive per kWh renewable energy
Example
EPRA14~18DAV3+W1 + ETBH/X16EF6V+9W
Daikin Altherma 3 H HT W
4P644736-1 – 2021.02
If you want to...
Enable the user to program a
quiet mode schedule
Only applicable in combination with the bivalent function. See also
4
"Bivalent" [
 208].
#
Code
[7.5.1]
N/A
[7.5.2]
N/A
[7.5.3]
N/A
[7.6]
N/A
INFORMATION
Electricity price can only be set when bivalent is ON ([9.C.1] or [C-02]). These values
can only be set in menu structure [7.5.1], [7.5.2] and [7.5.3]. Do NOT use overview
settings.
An incentive can be taken into account when setting the energy prices. Although
the running cost can increase, the total operation cost, taking into account the
reimbursement will be optimized.
NOTICE
Make sure to modify the setting of the energy prices at the end of the incentive
period.
This is an example and the prices and/or values used in this example are NOT
accurate.
Data
Gas price
Electricity price
Renewable heat incentive per kWh
Calculation of the gas price
Gas price=Actual gas price+(Incentive/kWh×0.9)
Gas price=4.08+(5×0.9)
Gas price=8.58
Calculation of the electricity price
Electricity price=Actual electricity price+Incentive/kWh
Then...
Select Automatic.
Result: The unit runs in quiet mode
according to a schedule. The user
(or you) can program the schedule
in [7.4.2] Schedule. For more
information about scheduling, see
"10.3.7 Schedule screen:
4
Example" [
 139].
Description
Electricity price > High
Electricity price > Medium
Electricity price > Low
Gas price
Price/kWh
4.08
12.49
5
10