! Caution:
If the Front Mounting Bracket is not attached to a frame member that
runs the full length of the gate, the gate operator may damage the gate. DO NOT
attach the bracket or backing plate to just a few pickets.
Mounting the Gate Operator
STEP 1
Front Mounting Bracket:
a. Position the bracket according to the
dimensions provided on pages 12-13.
b. Ensure the bracket is level and affix in
place.
!
The E-4 Operator MUST be mounted
level. The Front Bracket will be offset
lower than the Rear Bracket.
STEP 3
Mount the Gate Operator:
a. Install the Rear Mounting Bushing.
b. Install the operator onto the Front
Mounting Bracket first then the Back.
!
Ensure the E-4 Operator is level.
c. Manually Release the E-4 Operator.
Refer to page 7.
d. Manually move the gate to ensure the
gate and operator moves freely.
Check Operation
Through Entire
Range of
Movment
VIKING TECHNICAL SUPPORT 1.800.908.0884
GATE OPERATOR INSTALLATION
Refer to Dimensions
A & B for positioning
STEP 2
Back Mounting Bracket:
a. Position the bracket according to the
b. Ensure the bracket is level and affix in
!
STEP 4
Complete the Installation:
a. Dismount the operator.
b. Complete the welding process.
c. Lubricate the front bracket pivot point.
d. Reinstall the gate operator and verify
once again that the gate moves freely.
e. Rotate the Manual Release Handle
clockwise to the engage position.
3a
dimensions provided on pages 12-14.
place.
The E-4 Operator MUST be mounted
level. The Rear Bracket will be offset
higher than the Front Bracket.
Lead Screw Carrier
Front Mounting Bar
Small Flat
Washer
Lock
Washer
1 5