2.5. Run the Main System and Project

This section will describe how to start the main system and the project of the UA-5200 series.
When the user finish the project setting and want to start the system and project, simply click on
the "System Management" on the left tree-menu, scroll down the webpage to the "Main System
Setting" box, and then click the "status" switch.
1
While "ON" is displayed, it means the new project is running in the UA-5200 system.