2.8. System Start-Up

1. Remove cover and lid and pour ¼
cup of chlorine into the first chamber.
(This will disinfect the system.)
Replace the lid making sure all
screws are secure.
2. Check that all plumbing and
electrical connections have been
properly completed.
3. Slowly change bypass to the
"service" configuration. Check
for leaks.
3a. Manually open ASV using
Controller by pressing the OPEN button.
4. Turn power switch for AIRaider to
"On". The water inlet solenoid valve
will now open allowing water into
Figure 16
the system. The aeration process
Installed AIRaider 433-S50
will also start. Check for leaks.
5. Allow the AIRaider to fill
with water.
6. On 433-S50 & 433-S50X Systems the submersible pump installed in the Aeration Tank will self
prime when the rising water level lifts the pump float and the pump starts. (Follow pump manufac-
turer's instructions to prime other external pumps.) The normal operating range is nominally 40 PSI –
60 PSI* but will vary(Pressure Switches on 433-S50 & 433-S50X factory set at 38 PSI - 55 PSI approx.).
CAUTION: Do Not Attempt to Adjust the Pressure on 433-S50 or 433-S50X Systems, as this
may result in the pump not shutting down as it attempts to reach too high a set pressure.
This problem may not occur immediately but can occur later when a low voltage supply
occurs due to high electrical demand or other external factors. The factory pressure
setting is deliberately less than maximum to provide an allowance for a low voltage
supply event. Continuous operation of the pump when there is no water demand will overheat
the system causing the thermal overload to trip and consequent pump shut down.