Test Procedure
6 Test Procedure
6.1 Line and Load Regulation and Efficiency Measurement Procedure
1. Set up the EVM as
Section 4.2
2. Set the electronic load to draw 0 A
3. Increase V
from 0 V to 12 V using voltage meter to measure input voltage.
IN
4. Use the other voltage meter to measure output voltage V
5. Vary the load from 0 to 80 A
6. Vary V
from 5 V to 16 V. V
IN
7. Decrease the load to 0 A.
8. Decrease V
to 0 V.
IN
16
TPS546D24S 2-Phase SWIFT
User's Guide
and
Section 6.2
describe.
.
DC
. V
must remain in regulation as defined in
DC
OUT
must remain in regulation as defined in
OUT
™
Step-Down Converter Evaluation Module
Copyright © 2023 Texas Instruments Incorporated
.
OUT
Table