4.9 Test the Installation

Follow all precautions while testing the mast system installation.
To test the installation:
1. Review the Pre-Operation Check (Section 5.1) and prepare the mast system for
operation.
2. Extend the mast (Section 5.3.1).
3. Lower the mast (Section 5.3.3).
See Section 5 for additional details on these procedures.

4.10 Install the Payload

The exact installation procedures for payload will vary based on the customer-specific payload.
For optimal performance, center the payload as best as possible. If the payload must be offset,
offset the payload in-line with the keys. Contact The Will-Burt Company with any questions
before performing any installation procedures.
In general, to install the payload:
1. Carefully move the payload into position.
2. Properly secure the payload to the mast. The mounting hardware must include proper
means to resist vibration loosening, such as thread-locking compound or locking
hardware. Torque all hardware as appropriate for its size and grade.
Note: If securing a payload part-way along a mast tube, be sure not to overtighten the tube, or
damage to the mast could occur. Intermediate tube clamps are available to assist in attaching
payloads to the intermediate tubes. See www.willburt.com for additional information.