Pre Start-up Check List
Prior to taking the high pressure cleaner into operation, it is recommended to carry out
a few, basic checks. Not only will this eliminate the wasting of valuable time, trying to
operate the equipment by trial and error, but it will also minimize the possibility of costly
repairs and unnecessary downtime.
Operator Suitability
Is the person intended to operate the system sufficiently trained to do so in accordance
with the instructions, as detailed in this manual ?
Electricity / Water Mains Supplies Check
It is imperative that both utility supplies are checked, i.e. that the water supply valve is
in the open position and that the mains power supply to the machine is established.
Pump Oil Level Check
It is essential to carry out a pump oil level check prior to taking the unit into operation
for the first time and thereafter, at periodic, at least weekly intervals.
Cleaning Attachment Check
Verify that the cleaning attachments,- high pressure hose and spray lance have been
connected properly and made secure.