DAILY SAFETY CHECKS

1)
Labels & Manuals: Check all labels, placards and Operating & Safety manual (located in the box within the platform) are in place and legible.
2)
Structure: Check there are no loose, missing, damaged or malfunctioning components including but not limited to: chassis, booms,
platform, platform gate (free to close under gravity), all welds, guards, covers, boom clamps, brakes, wheels, tyres and outriggers /
stabilisers (if applicable). Ensure that platform is free from debris, grease or oil that could cause slipping or tripping hazards.
3)
Warnings & Switches: Check there are no loose, missing, damaged or malfunctioning components including but not limited to: platform
load sensor, tilt sensor and / or alarm horn, foot pedal, high engine and / or high drive limit switches, micro switches, lights and beacons.
4)
Controls: Check all operating, emergency and manual descent controls function correctly – select an area free from obstructions and
hazards, and exercise extreme caution.
5)
Hoses & Wiring: Check there is no damage to or leaks from hydraulic, fuel and air systems, electrical cables and wiring.
6)
Power Systems: Check batteries, engine oil and coolant (if applicable) for condition, cleanliness, connections and correct fluid levels.
7)
Personal Protective Equipment: Check that full body safety harnesses, short lanyards, and hard hats are in good condition and fit for
purpose.
2

SETTING UP PROCEDURE

1)
Position Niftylift on firm ground, bearing in mind range of boom movement so that any overhead obstructions or possible hazards such as,
but not limited to, power cables, telephone lines, drains, manhole covers, etc. can be safely avoided.
2)
APPLY HANDBRAKE: Chock wheels and cordon off the area using appropriate cones, barriers and flags.
3)
Levelling the machine using the hydraulic outriggers can accommodate a slope of up to 12 degrees, if necessary using suitable load bearing
pads to support the downhill jacks. Do not elevate the platform unless the base can be corrected to within three degrees of level.
4)
If the load bearing capacity of the ground is in any doubt the machine must NOT be used.
5)
Release boom travelling clamp.
6)
Check all red emergency stops are not engaged (i.e. fully out).
7)
Ensure that the key switch at the ground control station is turned to the "ON" position (i.e. clockwise).
8)
At the outrigger control station press down and hold the power lever on the right hand side. This activates the power and diverts hydraulic
flow to the legs for setting up. Then select the appropriate control lever to begin setup. Note: No power will be available if the booms are
not stowed onto the boom rest.
9)
Using the four outrigger control levers, lower each outrigger onto a firm, level surface and level the machine base ensuring each outrigger foot
is taking equal weight with the wheels clear of the ground. Note: Deploy the front two outriggers first to minimise the risk of damaging
the jockey wheel.
10) Check that the base is level using the spirit level adjacent to outrigger control station as a guide.
11) The booms can now be operated from the ground control station by pressing and holding the green power button. Note: If the klaxon alarm
sounds check that each outrigger is lowered and each footpad is taking equal weight.
12) Always lower booms fully before adjusting, raising, retracting or moving the outriggers in any way.