The recovery equipment shall be in good working order with a set of instructions concerning the equipment that is at
hand and shall be suitable for the recovery of flammable refrigerants. In addition, a set of calibrated weighing scales
shall be available and in good working order. Hoses shall be complete with leak-free disconnect couplings and in
good condition. Before using the recovery machine, check that it is in satisfactory working order, has been properly
maintained and that any associated electrical components are sealed to prevent ignition in the event of a refrigerant
release. Consult manufacturer if in doubt.
The recovered refrigerant shall be returned to the refrigerant supplier in the correct recovery cylinder, and the
relevant Waste Transfer Note arranged. Do not mix refrigerants in recovery units and especially not in cylinders.
If compressors or compressor oils are to be removed, ensure that they have been evacuated to an acceptable level
to make certain that flammable refrigerant does not remain within the lubricant. The evacuation process shall be
carried out prior to returning the compressor to the suppliers. Only electric heating to the compressor body shall be
employed to accelerate this process. When oil is drained from a system, it shall be carried out safely.
DECOMMISSIONING
Before carrying out this procedure, it is essential that the technician is completely familiar with the equipment and
all its detail. It is recommended good practice that all refrigerants are recovered safely. Prior to the task being
carried out, an oil and refrigerant sample shall be taken in case analysis is required prior to re-use of reclaimed
refrigerant. It is essential that electrical power is available before the task is commenced.
a) Become familiar with the equipment and its operation.
b) Isolate system electrically.
c) Before attempting the procedure ensure that:
-
Mechanical handling equipment is available, if required, for handling refrigerant cylinders;
-
All personal protective equipment is available and being used correctly;
-
The recovery process is always supervised by a competent person;
-
Recovery equipment and cylinders conform to the appropriate standards.
d) Pump down refrigerant system, if possible.
e) If a vacuum is not possible, make a manifold so that refrigerant can be removed from various parts of the
system.
f) Make sure that cylinder is situated on the scales before recovery takes place.
g) Start the recovery machine and operate in accordance with manufacturer's instructions.
h) Do not overfill cylinders. (No more than 80 % volume liquid charge).
i)
Do not exceed the maximum working pressure of the cylinder, even temporarily.
When the cylinders have been filled correctly and the process completed, make sure that the cylinders and the
j)
equipment are removed from site promptly and all isolation valves on the equipment are closed off.
k) Recovered refrigerant shall not be charged into another refrigeration system unless it has been cleaned and
checked.

CHARGING PROCEDURES

In addition to conventional charging procedures, the following requirements shall be followed.
-
Ensure that contamination of different refrigerants does not occur when using charging equipment. Hoses or
lines shall be as short as possible to minimise the amount of refrigerant contained in them.
-
Cylinders shall be kept upright.
-
Ensure that the refrigeration system is earthed prior to charging the system with refrigerant.
-
Label the system when charging is complete (if not already).
-
Extreme care shall be taken not to overfill the refrigeration system.
Prior to recharging the system, it shall be pressure tested with OFN. The system shall be leak tested on completion of
charging but prior to commissioning. A follow up leak test shall be carried out prior to leaving the site.
The safety wire model is 5*20_5A/250VAC, and must meet the explosion-proof requirements.
3 2