HELIOS CUBE BS4850-SH
User Manual
4.3 C
OMMISSIONING
Step 1.
Switch on the all battery modules as shown in Figure 4-3. The "RUN" light should become green.
Step 2.
Turn on the battery DC breaker in the cabinet.
Step 3.
Turn on the AC and DC breakers of the inverter.
Step 4.
Turn on the inverter according to the User Manual of the inverter.
Step 5.
Set the charge and discharge parameters of the inverter according to the User Manual of the inverter
as well as the specifications in Table 2-2 of this Manual.
4.4 O
PERATION
Make sure the cabinet door is closed and locked to prevent children or other unauthorized persons from
accessing the batteries during operation.
There exists high voltage inside the cabinet, which may cause an electric shock and result in serious injury, death,
or serious property damage from the device in operation
During a normal operation, the "RUN" light should be green and the SOC (status of charge) indicator shows
the operating status of the battery system (see Table 4-1)
Helios New Energy Technology (Australia) Pty Ltd
Figure 4-3 Switch on/off of the battery moduel.
4. Commissioning and Operation
23

Advertisement

Table of Contents
loading

Related Products for Helios CUBE

This manual is also suitable for:

Bs4850-sh

Table of Contents