3. Installation
Step 4
Fasten the module onto the cabinet by using 4 screws (see Figure 3-4)
Step 5
Connect the inverter battery terminals to the DC breaker in the cabinet as shown in Figure 3-5.
A DC breaker is built in the cabinet. Make sure it is in the OFF state before connecting to the inverter.
Read carefully the User Manual of the inverter to be installed.
Don't connect the positive and negative terminals of the battery reversely, which otherwise could have
serious consequences.
Battery short circuits may cause personal injury. The high transient current generated by a short circuit will
release a surge of power and may even cause fire.
Do not connect or disconnect battery cables when the inverter is running. Failing to do so may cause
electric shocks.
Do not connect any load between the inverter and the battery.
The recommended cable is AWG6 or the cross-sectional area is 16mm².
The cable between the battery and inverter should be less than or equal to 10 meters, and within 5 meters
is recommended
18
Figure 3-4 Fasten the battery module onto the cabinet
HELIOS CUBE BS4850-SH
Helios New Energy Technology (Australia) Pty Ltd
User Manual

Advertisement

Table of Contents
loading

Related Products for Helios CUBE

This manual is also suitable for:

Bs4850-sh

Table of Contents