Level Yard Level Level Rock Wall Rock Wall Property Property Slope Slope Property Ground Support Follows Slope Slope of Property Level Level Property Slope Property Slope *Eastern Jungle Gym models with an A-frame design do require a level area for installation.
Page 6
Accessories Identification 1-Roll of electrical tape...
Page 9
Wood and Kit Identification 5’ Monkey Bars 2 @ MONKEY BAR UPRIGHTS PART #M4478 1 @ MONKEY BAR OVERHEAD RIGHT PART #M4478R 1 @ MONKEY BAR OVERHEAD LEFT PART #M4478L 1 @ MONKEY BAR TIE LEFT PART #MT2412L 1 @ MONKEY BAR TIE RIGHT PART #MT2412R 8 @ MONKEY BAR RUNGS AND HARDWARE...
Page 10
Step #1- Monkey bar Upright 5’ Monkey Bars Layout (2) M4478 Monkey bar uprights and 3 15 1/8” monkey bar rungs. Make sure angled cut sides are facing in the same direction. Measure from the bottom of the uprights and make a mark as shown in the drawing.
Page 11
Step #3-Monkey Bar Assembly 5’ Monkey Bars Lay Monkey bar upright and overhead on the sides. Place angled cuts together as shown in drawing. Step #4-Monkey Bar Teak Install 5’ Monkey Bars Install MT2412R on the side of the upright and overhead as shown in drawing.
Page 12
Step #5 Monkey Bar Install 5ft Monkey Bars Place Monkey Bar assembly through bars in ½ wall. Level as needed. Install into post and tent top support using B5 bolts. Two metal stakes are provided for added stability. After swing beam is installed insert stakes into the ground flush with support legs.
Page 13
Step #5a Monkey Bar Install Option 2 5ft Monkey Bars Only for Straight Base models Place Monkey Bar assembly through bars in ½ wall. Level as needed. Install into post and tent top support using B5 bolts. Two metal stakes are provided for added stability.