This instruction booklet is to be used exclusively for Eastern Jungle Gym
customers only. It is not to be handed out to the general public. Any duplication of
this booklet will be subject to copyright protection and federal laws.
Last revised 3/30/2016

Advertisement

Table of Contents
loading

Summary of Contents for Eastern Jungle Gym Dream

  • Page 1 Manual Dream This instruction booklet is to be used exclusively for Eastern Jungle Gym customers only. It is not to be handed out to the general public. Any duplication of this booklet will be subject to copyright protection and federal laws.
  • Page 2 A little time now can save you time when your building! If you have any missing parts or damaged material or are having trouble installing your new Eastern Jungle Gym product. Please call Eastern Jungle Gym directly. or Email - Info@easternjunglegym.com...
  • Page 3 “Creating Childhood Memories” Play Safely Instructions 1) Do not let children play on your Eastern Jungle Gym product until it is fully and safely assembled. 2) Go over all safety points with children prior to letting them play. 3) Adult supervision is required for children of all ages.
  • Page 4 Many parts are heavy and could seriously injure a child. 2) Your ready to start your assembly process. You will need at least two adults to safely and easily assemble your Eastern Jungle Gym. 3) Wear safety glasses when drilling out wood to protect your eyes from flying wood clips.
  • Page 5 “Creating Childhood Memories” Hardware Identification (3) 16’ Sections Bag of 12 (6) Heavy Duty Rope Rocks with Hardware Swing Hangers 2 pair Safety Grab Handles (1) 10’ Wave Slide Ladder Rungs (1) Ring Trap Combo (1) Swing Beam Support Brace (6) Spring Clips (2) Green Items not shown:...
  • Page 6 “Creating Childhood Memories” SPECIAL NOTE BEFORE BEGINNING YOUR ASSEMBLY: All Recessed holes must be piloted with 1/4” drill bit to help minimize splintering. All lag bolts must be accompanied with a washer before driving in lag bolt. Now you are ready to begin assembling!
  • Page 7 Dream GROUND SUPPORT BASE Step #1 GS2455 R2455 R2455 5” R2455 3½ ” Layout ground support base boards. Measure 3½” and 5” in from each corner of both 2 - GS2455 GS2455’s (as shown in photo). 2 - R2455 (as shown in the photo).
  • Page 8 Dream POSTS Assembly Step #2 36½ ” P4496 Measure in 36½” from one side of P4496 posts Layout 4 - P4496 clubhouse post (as shown in the and draw a line (as shown in the photo). Do this photo). to all 4 posts.
  • Page 9 Dream FLOOR Assembly Setup #4 After leveling, fasten 4x4 post to ground support base using 4 - 3” lags (as shown in photo). Position first completed 4x4 First post completed (as shown post into the lowest corner of in photo).
  • Page 10 Dream FLOOR Assembly Setup #4 FJ2455 R2455 R2455 R2455 Countersink Countersink Holes Holes R2455 5” 3½ ” R2455 1 - 3” lag in each corner Measure 3½” and 5” in from each Layout floor joists Stand up floor joist on end and install corner of both GS2455’s (as...
  • Page 11 Dream FLOOR Installation Step #5 Place floor on post teaks that you leveled earlier. At this point all four post and floor should be level. NOTE: Make sure floor orientation match ground support base orientation when placing floor on post.
  • Page 12 Dream SLIDE WALL installation Step #6 SLIDE Wall 20½” 20½” WR2496 R2429 Install top wall rail, WR2496 Place bottom wall rail, R2429 on Install tent support TS4476 to flush with top of post using 2 - 3” floor and install into left post the center of WR2496 and to the lags on each side.
  • Page 13 Dream FULL WALL installation Step #7 Solid Wall 20½” 20½” WR2496 WR2455 Place bottom wall rail, WR2455 on floor and Install top wall rail, WR2496 flush with top of install to both posts using 2 - 3” lags on each post using 2 - 3”...
  • Page 14 Dream ACTIVITY WALL #1 installation Step #8 Activity Wall #1 R2455 Place rail R2455 from inside clubhouse flush with top of post and install with 2-3” lags on each side. Place wall board Wb54436 Place wall board, GH2436 from outside of clubhouse from outside of clubhouse 3½”...
  • Page 15 Dream ROCK WALL assembly Step #9 Counter sink holes face each other Start decking your rock wall Layout 2 - RWJ2470 Rock Wall Continue decking your rock wall using FB54648. Start right using FB54648 until it is joists (as shown in the photo).
  • Page 16 Dream ROCK WALL installation Step #10 Rock wall complete! Place rock wall into back opening. From under the clubhouse Hold top of rock wall flush with top fasten rock wall to post of floor (as shown in photo). using 1 - 3” lag on each side (as...
  • Page 17 Ladder Side WALL Installation Step #12 Ladder side Wall R2455 R2429 Place clubhouse center rail Place ½ wall rail R2429 flush Place wall board, R2455 from inside SP4436 flush with top of rail with edge of post and fasten clubhouse flush with top of post and and fasten with 2-3”...
  • Page 18 Dream LADDER Assembly Step #13 61” 50” 39” 28” 17” 6” 6” Counter sink holes face each other Counter sink holes face each other Layout 2 - LS4467 ladder rails and Measure from the top which is the Screw the ladder rungs into 6 - Ladder rungs counter sink holes side.
  • Page 19 JACOB’S LADDER TOP RAIL Step #15 Mount JT4484 Jacobs Ladder top rail onto clubhouse using 2 - 5” lags on each side. The JT4484 gets mounted under the wall top rails (as shown in photo). Through holes should be facing the ground and run parallel with the bottom rail mounted on the ladder.
  • Page 20 (as shown in photo) provided on tent top (as shown in photo) Dream JACOB’S LADDER Step #18 Layout 6 - JD2426 Jacob Ladder Thread rope through Jacobs Thread 3 ropes through first Rungs and 3 - ropes (16’ sections)
  • Page 21 Dream SWING BEAM Assembly Step #19 Layout CB46114 Swing Beam on the ground. Place swing hangers on beam using hardware Holes are pre-drilled for placement. provided. 12 @ 3/8 Hex Bolt (6½”) 24 @ 3/8 Washer 12 @ 3/8 Nut...
  • Page 22 Dream SWING BEAM Installation Step #20 Slide each SS44114 Side Layout 2 - SS44114 Side Slide Swing Beam into the Support leg into the Angled Angled Side Support Brace. Supports legs and the Angled Side Support Brace. Installing Side Support Brace.
  • Page 23 Dream SLIDE Installation Step #21 Install SB2420 slide block under floor Position slide in slide wall opening where slide opening is using 2” screws (as shown in photo) Make pilot holes in the slide with 1/4” drill bit and install using 2” Screws...
  • Page 24 Dream Accessory Installation Step #22 Install grab handles as needed Mount Binoculars on ½ wall next Mount Captain Wheel on TS4476 above rock wall and ladder.Or to slide opening (as shown in tent support (solid wall side) (as Measure up from floor decking shown in photo).
  • Page 25 “Creating Childhood Memories” Register Your Eastern Jungle Gym Remove this page, fill it out and return it to info@easternjunglegym.com Eastern Jungle Gym 30 Commerce Dr. Carmel, NY 10512 Name Address City State Zip Code Phone Number Where Purchased City State...
  • Page 26 In addition, for a period of Fifteen Years from the date of purchase, EJG warrants to...
  • Page 27 Carmel, NY 10512 Or email - info@easternjunglegym.com An Eastern Jungle Gym customer service rep will contact you by phone or email after reviewing the claim approximately 24 - 48 hours. If a part is covered under warranty, you the customer will be responsible for shipping and handling.

Table of Contents