Floor Preparation; Putting In Place Optitome 2040 - Lincoln Electric OPTITOME II Series Safety Instruction For Use And Maintenance

Table of Contents

Advertisement

D - ASSEMBLY AND INSTALLATION
TOOLS REQUIRED FOR INSTALLING THE MACHINE ON THE SITE

2 - FLOOR PREPARATION

The floor does not need any particular preparation for installing the machine;
however, we recommend a concrete floor for the machine to be satisfactorily stable.
Concrete screed in a single stretch (200 mm thick) made at least 21 days before
(standard BAEL 91). The thickness of the screed and its reinforcement are given for
guidance, and must be verified depending on the characteristics of the floor.
Single concrete longitudinal member. 20 Mpa (350 kg/m³) concrete with metal
reinforcement.
Flatness over the entire site with additional travelling tracks ± 10 mm.
30 mm level difference of screed (5 mm/m max.).

3 - PUTTING IN PLACE OPTITOME 2040

The components of the installation may only be transported using the slinging points
provided, with appropriate slinging equipment.
Check the flatness of the floor with an optical level and identify the high point.
1)
Installation of thee parts of the table,
D-16
- Level, accuracy 1/10 per metre
- Impact drill for concrete, for bit Ø16
- Decameter
- Chalk line
- Vacuum cleaner
- 24 mm open-ended spanner
- 24 mm ring spanner
See layout drawing supplied
1
Part 1
2
Part 2
3
Part 3
8695 4788 / A
OPTITOME HPC 2