How to Run System Test for Inverter Outdoor Units

Navigate to system optimization > system test > run test
On initial power-up the inverter heat pump or air conditioner will
»
display code E11, signaling that initial system test must be run.
System test is required to check the equipment settings and functionality.
»
Once selected, it checks the equipment for approximately 10-15
»
minutes. System test may exceed 15 minutes if there is an error.
While the system test is active "test running" message shows
»
up on the screen.
System test is complete only when display code E11 notice clears
»
from the seven segment LED display on the heat pump or air
conditioner. Please wait for test to complete and for code to clear.
As soon as the test completes, "test running" message is cleared
»
from the screen.
49

Hide quick links:

Advertisement

Table of Contents
loading
Need help?

Need help?

Do you have a question about the One+ and is the answer not in the manual?

Subscribe to Our Youtube Channel

Table of Contents

Save PDF