Step 14. Install the two supporting pieces when needed. Place the UVF11 unit in a proper
location.
Note: Cut the 1/4'' tubing (not included) using a sharp blade to an appropriate length to
avoid kinking. Ensure the tubing is fully inserted into the quick-fitting connection about half
an inch deep and secure the connection with the supplied blue clips.
Perform the following steps to complete the installation process:
a. After completing all plumbing connections, slowly turn on the water supply and check
for leaks. Also, check to see if water flow activates the UV light.
b. Allow the water to run for a few minutes to clear any air or dust potentially in the
reactor chamber.
c. Plug in the power for starting up.
d. The system is now ready to use.
The completed system connection should be as shown below.