1
+5V

6 Operation

6.1 Check list before operation

1. Check whether the system is firmly installed, and the installation position is suitable for operation
and maintenance.
2. All cables are correctly connected, properly distributed, and well protected, and no mechanical
damage is caused.
3. The selection of AC circuit breakers is correct.
4. The wiring terminals are securely installed, and the vacant terminals are sealed.
5. All safety signs and warning labels on the system are firmly and clearly visible
6.2 Operation
1. Confirm that the above check list meets the guideline
2. Turn on the AC circuit breaker
3. After the AC circuit breaker is turned on and the LED on the system is on, perform the following
operations
a)
If the blue power LED does not light up, check if the grid power cable is tightly inserted.
If the grid power cable is OK and tightly inserted, but unit is still not illuminating the
power button - please contact local Redx dealer.
b)
Install the APP or open web page according to the attached instructions, and then configure
the WIFI connection.
c)
Turn on the battery circuit breaker on the side of the system.
d)
Press the power button on the side of the system, then the system is in bypass state and
UPS port has output.
e)
Send charging command through the web or APP. The battery LED indicator on the panel
lights up, and the other LED indicators will light up according to the actual working status.
If the operation fails, troubleshoot the fault by referring to Chapter 9 in this manual.
f)
Note: Use the grid and the APP to activate the battery for the first-time operation.
Rev 20220610
Figure 5-5 - RS485 pins
Table 5-3 - RS485 pins details
2
485_A
RX2505PU
3
485_B
Page 21 of 32
4
GND