Table 3. Facility Requirements
Type
Electrical
Thermal
Rack (when rack-
mounted)

Quick installation checklist

This checklist provides a high-level overview of the basic installation process from the planning stage to
the point where the device comes online and is ready to be deployed. Completing all the tasks in the
suggested order ensures successful installation. Brocade recommends that you print this checklist and
take it to the installation site.
Pre-installation tasks
Review all installation requirements ahead of time as part of your site preparation. Careful planning and
site preparation ensures seamless installation, especially when installing multiple devices.
Table 4. Installation prerequisites
Task
Unpack the device.
Gather necessary components
and required tools.
Review the safety precautions.
Plan the installation.
6 IBM Storage Networking SAN128B-7: SAN128B-7 Installation, Service, and User Guide
Requirements
• Adequate supply circuit, line fusing, and wire size, as specified by the electrical
rating on the switch nameplate.
• Circuit protected by a circuit breaker and grounded in accordance with local
electrical codes.
See the Technical Specifications for complete power supply specifications.
• Ambient air temperature not exceeding 40°C (104°F) while the switch is
operating.
• All equipment in the rack grounded through a reliable branch circuit connection.
• Additional weight of the switch not to exceed the rack's weight limits.
• Rack secured to ensure stability in case of unexpected movement.
Task details or additional information
Take an inventory of the hardware components included in your
shipment. Refer to " Shipping carton contents" on page 9.
Review the time and items that are required at the beginning of
each chapter toensure that you have gathered all the necessary
components that are required for the following installation tasks:
• Chapter 3, "Mounting the switch," on page 10
• Chapter 7, "Power Supply Assemblies," on page 55
• Chapter 8, "Fan Assemblies," on page 61
• Chapter 5, "Installing Transceivers and Cables," on page 41
Refer to "Safety precautions" on page 5. For translations, refer to
"Caution notices" on page xi at the end of this guide.
Decide whether you want to install the unit on a flat surface or in
a rack. For rack installation, obtain the appropriate rack mount kit.
Refer to Chapter 3, "Mounting the switch," on page 10.
Complet
ed

Advertisement

Table of Contents
loading

Table of Contents