Tower Boom Lift Cylinder Installation

1. Support the main boom and tower boom, place the
tower lift cylinder on the turntable and align the holes.
Install the cylinder barrel pin and torque the bolt to 285
ft. lbs. (388 Nm). Use JLG Threadlocker P/N 0100011 on
bolts.
2. Remove caps from cylinder hydraulic lines properly and
install lines to cylinder as previously tagged.
3. Using auxiliary power, activate tower lift function and
extend cylinder rod until the cylinder rod bushing aligns
with bushings on boom.
5-68
4. Using an appropriate brass drift, drive the tower lift cyl-
inder rod end attach pin through the aligned bushings.
Secure pin and torque the bolt 35 ft. lbs. (48 Nm). Use
JLG Threadlocker P/N 0100011 on bolts.
5. Remove main boom support and lifting device support-
ing the upright.
6. Using all applicable safety precautions, operate the
boom functions. Check for proper operation and
hydraulic leaks. Secure as necessary.
7. Check fluid level of hydraulic tank and add fluid, if
required.