Advertisement

Quick Links

INSTALLATION GUIDE
Actionair CSS Installation Guide
Contents
Installation Methods ...............................3
Horizontal Damper Installation in a Slab ......................... 5
Periodic Maintenance ..............................6
Wiring Diagrams ....................................8
Dimensions ...........................................9
Troubleshooting ....................................10
Drawings
Please visit our website to download the installation dra-
wings, which are located on the relevant product down-
load section.
Applies to...
• Actionair CSS
Health and safety
• This process must be undertaken by a competent
person. More than one person may be required to
ensure the safe handling of large dampers and other
materials. Use must be made of access equipment to
ensure unsafe practices are not used to approach walls
or difficult access areas.
• Standard site PPE should be used (minimum steel toe
cap boots, hard hat) together with any protective eye
wear, gloves and masks, when drilling or cutting is
being undertaken. The latter should also be used when
handing the wall construction materials, as defined by
the material suppliers. If loud equipment is being used,
hearing protection should be used.
• All waste materials should be collected and disposed of
as defined by the relevant supplier.
• Care must be taken when installing and inspecting
dampers, as they are likely to close without warning
due to loss of electrical power, or a temperature rise in
the ductwork. This is their prime function.
• Do not introduce any items, fingers or limbs inside the
damper casing.
• Larger dampers are heavy and must be handled in
accordance with current local regulations and good
practice.
• All wiring should be carried out in accordance with the
wiring details provided, to the IEC regulations.
• Dampers are life safety products and must be treated
with care during handling, storage and installation.
• Actionair CSS Dampers are designed for applications in
normal dry filtered air systems and should be subjected
to a planned inspection programme.

Advertisement

Table of Contents
loading

Summary of Contents for Swegon Actionair CSS Series

  • Page 1: Table Of Contents

    INSTALLATION GUIDE Actionair CSS Installation Guide Contents Drawings Please visit our website to download the installation dra- CE Installation Method Overview ....2 wings, which are located on the relevant product down- Installation Methods .......3 load section. Vertical Damper Installation in a Plasterboard Wall ..3 Applies to...
  • Page 2: Ce Installation Method Overview

    BS EN 12101-8 and drive open, drive closed without failsafe position, see our website for informa- tion on the Actionair SmokeCommand smoke con- trol damper documentation and suitable installation methods. Swegon reserves the right to alter specifications. 20220627 LNNN00356 (5.4)
  • Page 3: Installation Methods

    250mm studs and tracking surrounding the aperture. between openings, then this takes precedence over our guidance. 8. Clean damper and actuator from any debris. LNNN00356 (5.4) 20220627 Swegon reserves the right to alter specifications.
  • Page 4: Vertical Damper Installation In A Masonry Wall

    (minimum M4x60mm) securely fix damper flange to wall. 6. Clean damper and actuator from any debris. 7. Perform commissioning and maintenance procedure, as described in BS9999;2017, either electrically by pressing Swegon reserves the right to alter specifications. 20220627 LNNN00356 (5.4)
  • Page 5: Horizontal Damper Installation In A Slab

    (minimum M4x60mm) securely fix damper flange to wall. • Clean damper and actuator from any debris. • Perform commissioning and maintenance procedure, as described in BS9999;2017, either electrically by pressing LNNN00356 (5.4) 20220627 Swegon reserves the right to alter specifications.
  • Page 6: Periodic Maintenance

    • A comprehensive example of the maintenance pro- cedure is given in Annex D of the standard. Some Swegon reserves the right to alter specifications. 20220627 LNNN00356 (5.4)
  • Page 7 This may be done after the initial installation test, to provide periodic operation of the damper to simulate actual fail-safe closure under fire conditions. • Note: Application of supply voltage will automatically override the manual locking mechanism. LNNN00356 (5.4) 20220627 Swegon reserves the right to alter specifications.
  • Page 8: Wiring Diagrams

    Actionair CSS Installation Guide Wiring Diagrams CSS Mode 5 CSS Mode 6 IP54 rated CSS Mode 5-3P Swegon reserves the right to alter specifications. 20220627 LNNN00356 (5.4)
  • Page 9: Dimensions

    • 100/3.5 • 125/3.9 • 150/4.5 • 160/4.7 • 200/5.4 • 250/6.5 • 300/7.5 • 315/7.9 • 350/8.6 • 355/8.7   Below        LNNN00356 (5.4) 20220627 Swegon reserves the right to alter specifications.
  • Page 10: Troubleshooting

    Foreign matter is impeding Check and remove blade movement Motor location pointer omit- Fit new pointer Mode not screwed down Check and tighten correctly Swegon reserves the right to alter specifications. 20220627 LNNN00356 (5.4)
  • Page 11: Inspection And Handover Check Sheet

    Inspection and handover check sheet This certificate applies only to Swegon Fire Dampers. The installer must complete this installation certificate when instal- ling fire and smoke dampers. A separate certificate must be completed for each individual fire and smoke damper.

Table of Contents