If the inverter has already been activated and commissioned:
l
 a.  If not already ON - turn ON AC to the inverter by turning ON the circuit breaker on the main 
distribution panel. 
 b.  If not already ON - move the Connection Unit switch to the ON position.  
 c.  Open   S etApp and follow the instructions on the screen (scan the inverter bar-code; move the 
ON/OFF/P switch to P position (for less than 5 sec) and release). 
The mobile device creates a Wi-Fi connection with the inverter and displays the inverter main 
Status screen.
Power
100 kW
P_OK: 138 of 141
Optimizers Connected
Status
Production
CosPhi
1.00
Voltage
850 Vdc
Commissioning
 d.  Tap Commissioning at the bottom of the screen. The main Commissioning menu screen is 
displayed.
In the main   m enus, tap the menu red arrows (
task. Tap the Back   a rrow (
The next sections provide more information about configuration options (in addition to Country and
Language and Pairing, described in Step 2: Commissioning and Configuring the Installation on page 36).
 
 
Three Phase Inverter with synergy technology Guide MAN-01-00402-1.1
Chapter 5: Activating, Commissioning and Configuring the System Using SolarEdge
Status
Inverter
SN 07318000C
Voltage
Frequency
277 Vac
60.9 Hz
S_OK
Server Connected
Switch
ON
Limit
Country
No Limit
Netherlands
Temp
Fan
156 F
OK
) to perform the system commissioning or configuration 
) to return to the previous menu.
37