Mounting and Connecting the Primary and Secondary Unit(s)
 2.  To allow proper heat dissipation, maintain the following minimum clearance areas between the 
inverter and other objects: 
NOTE
The Primary unit is longer than the Secondary Unit, therefore make sure the mounting location is
high enough to fit the Primary Unit and leaves sufficient space for cable entry.
 
If installing a single inverter:
l
 
At least 20 cm (8") from the top and bottom of each unit. For the Primary Unit, make sure to 
o
leave sufficient clearance for cable entry. 
 
3 cm (1.2")   f rom the right and left of the unit. 
o
 
If installing multiple inverters:
l
 
When installing inverters one above of the other, leave at least 40 cm (16") between inverters. 
o
When installing the Primary Unit , leave 40 cm (16") between the top of the Primary Unit and 
the bottom of the Connection Unit.
 
When installing inverters side by side:
o
Location
Locations where the annual
average high temperature
below 25˚C / 77˚F
Locations where the annual
average high temperature
above 25˚C / 77˚F
 3.  Position the mounting brackets against the wall and mark the required drilling holes locations with 
the supplied level. The level markings correspond to a distance of 3 cm between units
 4.  Drill two holes for each bracket and mount the brackets.
 5.  Put in the screws without tightening in order to correct positioning.
 6.  Place the level beneath the brackets   a nd align the brackets, tighten the screws all the way and verify 
that the brackets are firmly attached to the mounting surface. 
 7.  Mount the Primary Unit:
1
Annual average high temperature – the average of the 12 monthly average highs, for example:
Refer to
http://www.weatherbase.com/
24
Three Phase Inverter with synergy technology Guide MAN-01-00402-1.1
Indoor Installation
20 cm / 8"
1
is
between inverters
40 cm / 16"
1
is
between inverters
to find the value in your location.
Clearance
Outdoor Installation
5 cm / 2" between inverters (if
inverters are also installed one above
the other, maintain the indoor
installation clearance)
 