4.9 Leakage control

When making a leakage control of the gas supply system the solenoid valve
should be closed. Connect a pressure gauge to the test nipple Pa, see fig.
The test pressure in the system should be 1,5x max. inlet pressure or min.
150 mbar. If any leakage, locate the source by means of soapy water or a
leak location spray. After tightening repeat the test.
Electric function test:
Ensure that phase and neutral are not reversed. The gas shut-off cock
should be closed.To prevent the gas pressure switch from locking out it
should be linked temporarily.
After the main switch has been switched on and the thermostats have been
adjusted the pre-purging period begins (30-35sec.). At the end of this period
the pre-ignition period starts (0,5-2,5 sec. dependent on the design of the
gas control). The gas valve is energized and opens and flame is established.
At the end of the safety time (2-3 sec.) the gas control locks out. The
solenoid valve and the motor will be "dead". Remove the link from the gas
pressure switch after the test is finished.