Commissioning

9.1

Commissioning Procedure

This section describes the commissioning procedure and gives an overview of the steps you must
perform in the prescribed order.
Commissioning an inverter that is captured in a communication device
When the inverter is captured in a communication device, the communication device (e.g.
SMA Data Manager) is the unit for configuring the total system. The configuration is
transferred to all inverters in the system.
• Commission the inverter (see Section 9.2, page 47).
• The initial configuration of the inverter is made via the communication device. The
configuration is transferred to the inverter and the settings of the inverter are overwritten.
Procedure
1.
Commission the inverter.
2.
Establish a connection to the user interface of the inverter.
There are various connection options to choose from for
this:
• Direct connection via Ethernet
• Connection via Ethernet in the local network
3.
Log into the user interface.
4.
Configure the product and set country data set. Then the
product will begin operation.
5.
Make further inverter settings as needed.
9.2

Commissioning the Inverter

Requirements:
☐ The AC circuit breaker must be correctly rated and mounted.
☐ The product must be correctly mounted.
☐ All cables must be correctly connected.
☐ Unused enclosure openings must be sealed tightly with sealing plugs.
Operating manual
9 Commissioning
See
Section 9.2, page 47
Section 10.1, page 49
Section 10.2, page 50
Section 10.6, page 53
Section 10, page 49
STP110-60-BE-en-13
47

Advertisement

Table of Contents
loading

This manual is also suitable for:

121619-00.01

Table of Contents