VFD Cooling System Leak Inspection
1. Check for leaks on the refrigerant cooling flange connec-
tions to the VFD enclosure.
2. Check for leaks on all tubing internal to the VFD enclo-
sure, the tubing flair connection to the VFD module and
the TXV valve.
3. Verify that the VFD refrigerant cooling system TXV
valve control bulb is securely inserted into the VFD drive
module heat sink.
Power Up Verification
1. Inspect control wiring inside the VFD and verify the in-
tegrity of the connections between the integrated starter
module (ISM) and the VFD module.
2. Close the control power switch in the VFD enclosure.
3. Close the oil pump power switch inside the VFD
enclosure.
4. Verify the VFD disconnect switch is in the open position.
5. Close and latch the doors of the VFD enclosure.
6. Apply power to the VFD enclosure. Remove lock outs
and close all disconnects.
7. Verify that the CVC/ICVC display powers up and goes to
the default screen.
8. Close the VFD disconnect switch.
9. Verify the following actions during the VFD start-up self
test:
• The display shows SELF and all LEDs are illumi-
nated for 5 to 6 seconds.
• The display reads a 0 after the diagnosis is
complete.
• If Err is displayed a fault has been detected.
Perform manual reset by establishing a reset
through the small hole under the VFD Keypad. If
this does not correct the fault contact your Carrier
representative.
• If AR with a counting down number is displayed
wait for the number to count to 0 and the display
should then revert to a 0. If the counter starts over
at 30 contact Carrier representative.
Configure VFD Parameters — The VFD controller must have
job specific parameters set as defined by the component name-
plates and labels. The parameters come preset by the factory,
but must be verified prior to start-up by accessing the PRO-
GRAM MODE of the VFD controller keypad. For information
on how to access the VFD keypad see page 58.
Press the
PROGRAM
softkey to access the parameter
screen to modify or view the following job specific parameters:.
VFD
TITLE
PARAMETER
P.004
Maximum
Line Frequency selected. Per
Speed
Compressor Nameplate.
P.006

Password

107
P.028
Speed
60 for 60 Hz selection and
Display
50 for 50 Hz selection
Scaling
H.000
Motor
Compressor nameplate voltage.
Voltage
H.001
Frequency
Line Frequency selected. Per
Compressor Nameplate.
H.002
Motor
Compressor nameplate amps.
Amps
H.021
Line
VFD nameplate voltage.
Voltage
H.022
Over
69 for 60 Hz selection and
Frequency
57 for 50 Hz selection.
Limit
SETTING
59
Configure Chiller Visual Controller Parameter — The chiller
controller must have its job specific parameters set as defined
by the job sheet or installed nameplates. Below are the job spe-
cific parameters that must be set:
To access the ISM_CONF screen:
1. Press
.
ENTER
2. Press
.
SERVICE
3. Enter the password 1111.
4. Select ISM (CONFIG STARTER DATA)
5. Scroll down and select the ISM_CONF DATA screen to
modify or view the ISM parameters:
DESCRIPTION
STARTER TYPE
2
(2 = SS/VFD)
MOTOR RATED
VFD Nameplate Voltage.
LINE VOLTAGE
MOTOR RATED
VFD Nameplate Chiller Rated Load
LOAD AMPS
Amps
MOTOR LOCKED
Compressor Nameplate
ROTOR TRIP
STARTER LRA RATING
600 for VFD
part #19XVR0414XXX
700 for VFD
part #19XVR0500XXX
900 for VFD
part #19XVR0643XXX
MOTOR CURRENT
163
CT RATIO:1
120 (414A)
3 GRND FAULT CT?
NO
(1=NO)
FREQUENCY-60HZ
NO for 50 Hz selection
(NO=50)
YES for 60 Hz selection
6. Press to the
softkey to save changes.
SAVE
7. Press the
softkey to and exit the ISM Configura-
EXIT
tion Screen.
VFD Enable Configuration — To access the parameters:
1. Press
.
MENU
2. Press
.
SERVICE
3. Select EQUIPMENT SERVICE.
4. Scroll down and select SETUP2.
5. Verify the following parameters:
VFD OPTION
ENABLED
VFD CURRENT LIMIT
COMPRESSOR NAMEPLATE AMPS
Configure Surge Parameters
1. Press
.
MENU
2. Press
.
SERVICE
3. Select EQUIPMENT SERVICE and OPTIONS to verify
the following:
DESCRIPTION
SURGE/HGBP
Surge parameter label
DELTA T1
SURGE/HGBP
Surge parameter label
DELTA P1
SURGE/HGBP
Surge parameter label
DELTA T2
SURGE/HGBP
Surge parameter label
DELTA P2
VFD CONTROL VERFICATION (Non-Running) — In order
to verify and, if necessary, tune the speed control signal of the
chiller controller to the VFD (ISM terminal J8 1-2 labeled
4-20 mA OUT VFD) and the speed feedback signal from the
VFD to the chiller controller (ISM terminal J6 1-2 labeled
VFD HZ), follow the steps below.
Set TARGET VFD SPEED to 0%.
1. Press
MENU
.
SETTING
SETTINGS

Hide quick links: