Advertisement

Quick Links

Guide of ITS Construction
Hikvision ITS Construction
Guide
0

Advertisement

Table of Contents
loading
Need help?

Need help?

Do you have a question about the ITS and is the answer not in the manual?

Questions and answers

Subscribe to Our Youtube Channel

Summary of Contents for HIKVISION ITS

  • Page 1 Guide of ITS Construction Hikvision ITS Construction Guide...
  • Page 2 INCIDENTAL, OR INDIRECT DAMAGES, INCLUDING, AMONG OTHERS, DAMAGES FOR LOSS OF BUSINESS PROFITS, BUSINESS INTERRUPTION, OR LOSS OF DATA OR DOCUMENTATION, IN CONNECTION WITH THE USE OF THIS PRODUCT, EVEN IF HIKVISION HAS BEEN ADVISED OF THE POSSIBILITY OF SUCH DAMAGES.
  • Page 3 SURVEILLANCE LAWS VARY BY JURISDICTION. PLEASE CHECK ALL RELEVANT LAWS IN YOUR JURISDICTION BEFORE USING THIS PRODUCT IN ORDER TO ENSURE THAT YOUR USE CONFORMS THE APPLICABLE LAW. HIKVISION SHALL NOT BE LIABLE IN THE EVENT THAT THIS PRODUCT IS USED WITH ILLEGITIMATE PURPOSES.
  • Page 4: Table Of Contents

    Guide of ITS Construction Contents CHAPTER 1 PREPARATION ....................4 ..........................4 OOLS ........................ 4 ECHNICAL EVIEW CHAPTER 2 CONSTRUCTION METHODS ................5 ................. 5 ONSTRUCTING AND EQUIREMENTS 2.1.1 Excavation Requirements ..................5 2.1.2 Excavating Pole Base ....................5 2.1.3 Installing Grounding Stick ..................
  • Page 5: Chapter 1 Preparation

    Guide of ITS Construction Chapter 1 Preparation 1.1 Tools Reflective vest Safety rope Safety helmet Working clothes Gloves Protective tools Safety sign Traffic cone Plastic road barrier Warning lines Measuring wheel Tape measure Positioning tools Flexible tape measure Spray paint Excavation tool (shovel, mattock, etc.)
  • Page 6: Chapter 2 Construction Methods

    Guide of ITS Construction Chapter 2 Construction Methods 2.1 Pole Base Constructing and Requirements 2.1.1 Excavation Requirements The depth and width of pole base must comply with the requirements in the drawing. If the actual conditions do not meet the requirements, ensure that the volume of the pole base equals to that in the design.
  • Page 7: Installing Grounding Stick

    Guide of ITS Construction 2. Construction waste must be removed and disposed of in specified locations in time. 3. When excavation is finished, clean the sludge and drain the underground water, if any. Excavation Figure 2-2 2.1.3 Installing Grounding Stick Drive the grounding stick and slab into the bottom of the base based on the drawing to ensure the pole is entirely grounded.
  • Page 8: Installing Reinforcement Cage

    Guide of ITS Construction 2.1.4 Installing Reinforcement Cage 1. Place the cage at the center of the base, use level ruler to adjust its position. 2. Pay attention to the angle how the foundation bolts are placed to ensure the arm will be perpendicular to the road.
  • Page 9: Base Surface Processing

    Guide of ITS Construction Stirring Concrete Figure 2-5 2.1.6 Base Surface Processing 1. After concreting is finished, trowel the surface even and flat. 2. Maintenance for concrete is at least 20 days. 28 days is best. Troweling Figure 2-6 2.2 Constructing Cabinet Base...
  • Page 10: Constructing Handhole

    Guide of ITS Construction 600 mm cabinet, the base pit should be 800 × 800 mm, and 600 mm deep. 2. Erect support plates around the pit and they should be 100 mm higher than the ground. Then lay the pipeline properly. Generally, 6 × φ50PVC pipes are recommended.
  • Page 11: Lightning Protection And Grounding System

    Guide of ITS Construction 5. After the cables are laid, the remaining cross section of the pipes should be at least 40%. 6. Reserve galvanized wires in the pipes to lead the cables. 7. Restore the greenery. 8. Pipe jacking and overhead piping can also be used in addition to excavation, depending on the actual environment.
  • Page 12 Guide of ITS Construction Grounding Stick Figure 2-9 Welding Flat Steel Figure 2-10 Lead the grounding wire from the flat steel into the cabinet. Use flexible stranded copper wire of 10 mm cross section. Make sure the ground resistance is under 4Ω. If the test result failed the standard, it is...
  • Page 13: Installing The Pole

    Guide of ITS Construction Increase Grounding Area Figure 2-11 The distance between two angle steel should be more than 3 m and the two steel pieces should be welded with flat steel. The angle steel can be buried with PE pipes when digging the pipe groove, or the grounding stick can be installed after the site is recovered.
  • Page 14 Guide of ITS Construction Hoist the Pole Figure 2-12 Adjust the Erection Figure 2-13...
  • Page 15: Chapter 3 Example

    Guide of ITS Construction Chapter 3 Example Completed Installation Figure 3-1 Completed Installation Figure 3-2...
  • Page 16 Guide of ITS Construction...

Table of Contents