The following is the sequence of steps for closing and opening the circuit-breaker:
1.
Check that the circuit-breaker is open (open / closed indicator "O - OPEN"), and check that the springs
are discharged (spring signalling device "white - DISCHARGED SPRING") as indicated in Figure 24.
2.
Charging the springs - Pull the lever [A] downwards several times until the springs charged signalling
device [B] is "yellow - CHARGED SPRING" as indicated in Figure 25.
Figure 24
3.
Check that the circuit-breaker is open (open/closed signalling device "O - OPEN"), and check that the
springs are charged (springs signalling device "yellow - CHARGED SPRING") as indicated in Figure 26.
4.
Closing - Press the closing pushbutton "I - Push ON" as indicated in Figure 27.
Figure 26
5.
Check that the circuit-breaker is closed (open/closed indicator "I - CLOSED"), and check that the
springs are discharged (spring signalling device "white - DISCHARGED SPRING" as indicated in
Figure 28.
6.
Opening - Press the opening pushbutton "O - Push OFF" as indicated in Figure 29.
Figure 28
A
B
Figure 25
Figure 27
Figure 29
Continued on the next page